CHERRY COUNTY, NEBRASKA

TK Angus

From the permit to the monitoring record.

The current focus is water monitoring

The August 13 permit is background to the work now being tracked: installed wells, sampling reports, agency review, and completion records. Start with the monitoring plan and status list.

MONITORING RECORD · NOVEMBER 2, 2026

A new monitoring letter to follow

PCC’s October 29 review of the DWEE facility docket identified a groundwater-monitoring letter dated October 21, 2026. The next step is to review the original letter alongside the August monitoring plan and track the records that show what happens in the field.

What PCC is tracking

The docket entry alone does not establish agency approval, completed well installation, contamination or a violation. The original letter and approved plan still need a detailed comparison.

Open the DWEE facility docket: Facility 124885, LWC; October 21 “GROUNDWATER MONITORING” entry, document 20260109574. Read the monitoring-plan summary.

What the permit requires

Written approval before use

Condition 2 requires a completion certification and written DWEE approval before operating the new waste-control facilities.

Well locations

Condition 3 requires as-built plans showing all onsite wells after construction.

Monitoring

Condition 4 requires a site-specific plan and implementation of an approved plan upon completion of construction.

Scope

The permit lists 4,999 proposed swine of at least 55 pounds, 600 existing exempt feeder cattle, and two underfloor deep-pit barns.

Source: August 13 permit, record 20260091375. [5]

What DWEE said

In its August 14 response, DWEE said the application met Title 130 requirements. The response describes post-construction inspection, review of land-application records, and groundwater-result review. It also says county and Natural Resources District requirements remain separate. These are the agency’s statements and responsibilities; they do not document completion of each later step. [5]

FEDERAL RECORDS · OCTOBER 20, 2026

USDA records request closed: limited NRCS release

Status: closed. USDA FPAC issued its final response to PCC request 2026-FPAC-BC-07490-F on October 20, 2026. USDA located three pages of NRCS CRET mapping/footprint material: two pages released with partial redactions and one page withheld in full.

The released records include an initial pedestrian survey dated December 17, 2025, marked with a “Negative” survey result, and an Environmental Evaluation Summary dated April 15, 2026 identifying Project ID “TK Angus.” Project practices, land-use information and other details were redacted under FOIA Exemptions 3 and 6.

USDA separately reported that a search by the Farm Service Agency (FSA) identified no responsive FSA records for TK Angus Co. or Tim Marlatt. This does not contradict the existence of records held by NRCS, a different USDA agency.

What these records do not show: This limited, redacted release does not establish whether federal funding was awarded, whether a particular project received federal approval, or the adequacy or outcome of a comprehensive environmental review. The “Negative” entry is a result reported for one pedestrian survey, not a conclusion about all potential environmental impacts.

Read the redacted USDA release (3-page PDF) · Source index [13]. PCC is considering whether a narrow records appeal or clarification would add useful information; no appeal is represented here as filed.

Earlier decisions

The state permit was issued August 13, 2026. The public-comment period described in DWEE’s response ended July 31. Earlier county decisions and pre-permit research belong in the historical record. [5]

Read the historical materials · County meeting archive